Article · 18 November 2026
Brussels put storage inside its permitting fast-track
EU negotiators agreed the permitting directive that speeds up renewables, grids and storage, Greece named 4.7 GW of merchant batteries for connection terms while Cyprus could not connect six, and Poland's solar auction cleared far below its reference price.

In the seven days to 18 November, EU negotiators closed the first half of the European grids package, Greece named the merchant batteries that will be offered connection terms, and Poland’s regulator sold barely a third of the solar volume it put up. Most of what moved was about access rather than price: who is allowed to connect, how long an authority has to decide, and what has to be proved before a megawatt counts.
Brussels agreed to fast-track permits, and storage is named in the text
The Council said on Wednesday morning that it had reached a provisional agreement with the European Parliament on the permitting directive, which speeds up permits for renewable energy projects, electricity grids and storage facilities. Member states will be able to fast-track deployment by deeming those projects to be in the overriding public interest. The directive amends the renewable energy directive, the electricity market directive and the gas market directive, all three at once.
The deal completes the first half of the European grids package, the infrastructure plan the Commission put forward in late 2025. Ireland’s minister for climate, energy and the environment, Darragh O’Brien, said it delivered on the ambition in the One Europe, One Market roadmap. Nothing binds yet. Both institutions still have to endorse the text, which then goes through legal-linguistic revision before formal adoption, and member states get a year and a half after that to write it into national law.
For anyone who develops, owns or finances BESS, PV or flexible C&I load in the EU, the useful date is the one your own member state lands on, and there will be twenty-seven of them. Permit durations, what counts as overriding public interest when a consent is challenged, and which authority answers for a storage asset are all settled in transposition. So the work worth starting now is a file per market: the deadlines that apply today, the authority that holds them, and a named person watching them change. A project sitting in a queue this morning gets nothing from this agreement.
Fusebox builds custom software on the same platform that runs its flexibility operations, and one of those builds is a Knowledge Hub: a company memory that captures what people learn while they work and in handovers, so it stays when they leave. Anyone asks in their own words and gets the same answer, with the source it came from. It was built first for our own team, where it runs as Fusie, and it is now set up for other companies, each under its own name, with everything kept inside the company. When one directive becomes twenty-seven national rewrites over the next eighteen months, that memory is where the answer to what changed in Spain should sit.
Bring us the problem your team keeps re-solving →
Greece cleared 4.7 GW of merchant batteries, Cyprus could not connect six
Greece’s Ministry of Environment and Energy released its list of merchant battery projects, and 4,700 MW will receive connection terms. The ministry had taken 831 applications for 12,319 MW, of which 221 projects totalling 10,521 MW were for the transmission network and 610 projects totalling 1,798 MW for distribution. Evaluation left 6,366 MW as frontrunners or substitutes on transmission and 1,403 MW on distribution. None of the new volume carries support. The 900 MW that won subsidy in earlier auctions only began operating this year, and everything on this list is meant to run on market revenue. Public Power Corporation took five projects for 470 MW, most of them in coal regions, Masdar’s Terna Energy has 197.5 MW, Rokas 220 MW and Aenaos 198 MW. The government is aiming at 5 GW to 7 GW in operation by 2028, and the two network operators will issue connection terms in phases.
Cyprus shows the same process from the other end. Five of the six batteries that CYPV Solar Holdings installed at its solar parks in July, 24 MW and 55.6 MWh in total, are still waiting for connection terms, and the company says the applications it filed in 2025 carried documentation identical to the one that was approved. Its appeals have gone unanswered. Cyprus has installed a little over 1 GW of PV and curtailed more than 65% of potential solar generation between January and May this year.
For the BESS owners and portfolio managers in southeast Europe, the merchant volume has just been handed out, and with it the obligation to earn all of it. A battery with no support collects from day-ahead, intraday, balancing and whatever ancillary products the market opens, and it has to do that from its first month in operation. Connection terms are being issued in phases, which is exactly the window in which to settle the route to market, the metering and the prequalification, so that an energisation date and a revenue date are the same date.
Talk to Fusebox about a route to market for a merchant battery →
Italy has a million small batteries and a pipeline waiting on finance
Terna counted more than 1 million electrochemical storage systems attached to renewable installations at the end of October, 12.84 GWh and 6.5 GW of output between them.
The utility-scale half reads differently. Key to Energy told pv magazine Italia that Italy needs about 50 GWh of new utility-scale storage between 2024 and 2030, and a similar amount again in the decade after, as solar heads toward a projected 137 GW. Projects are not the constraint: more than 20 GW of BESS developments are already authorised, representing more than 130 GWh, enough on their own to meet the 2040 figure. About 19 GWh of electrochemical storage is in place today, including 7 GWh of utility-scale systems that arrived through capacity market auctions, and another 14 GWh is contracted and due. More than 30 GWh still has to be procured for 2030. The consultancy puts the average captured spread for a four-hour battery at EUR 30 to 40/MWh in 2030 and about EUR 50/MWh in 2040, and says MACSE has drawn supply exceeding demand by more than seven times, with financing of merchant exposure deciding how much of the pipeline is actually built.
If you run PV with batteries behind a meter in Italy, or a C&I site that could, those million systems are individually invisible to the market, because each one is far below the smallest volume an exchange or a TSO will take. Pooled, they can be offered where the price moves. The work is unglamorous and specific: telemetry per site, metering that matches settlement, and a participation rule per product, after which the portfolio holds one position instead of a thousand. If you want the product details for a given market first, ask Fusie.
Let us pool your Italian sites into one market position →
Poland’s solar auction cleared low and left most of the volume unsold
Poland’s Energy Regulatory Office awarded about 1.81 GW of solar in the auctions held on 9 and 10 November, with photovoltaics taking 65 of the 68 winning bids. In the category above 1 MW, 50 bids from 22 developers brought in 1,799 MW of solar and 64 MW of onshore wind, at prices from PLN 180/MWh to PLN 327.77/MWh against a reference price of PLN 389/MWh. That contracted roughly 17.7 TWh, around 33% of the volume on offer, worth more than PLN 5.5 billion. The category up to 1 MW did worse: 18 solar bids totalling 15.6 MW cleared at PLN 320/MWh to PLN 377.77/MWh against a PLN 414/MWh reference, taking 1.3% of the volume available. The hydro, agricultural biogas and biomass auctions produced no successful bids at all. The rounds had been announced at the start of the month in those same two capacity categories.
If you manage a Polish PV portfolio or trade around one, read the clearing prices and the unsold volume together. Bids came in as low as PLN 180/MWh against a PLN 389/MWh reference, and most of what was offered found no taker. Whatever does get built at those levels will generate in the same midday hours the existing fleet already fills, which is where a battery, a shiftable load or a charging plan changes the number at the bottom of the invoice. If your Polish sites still sell everything at the spot shape, that is the gap to close first.
Talk to us about shifting a Polish PV portfolio →
What to watch
- 24 November: Terna runs the second MACSE auction, 16 GWh for 2029 delivery on 15-year contracts, after the first round procured 10 GWh for 2028.
- 26 November: NESO’s Storage Behind Constraints consultation closes, after a month of comment on its shortlisted options.
- 22 December: applications close in Portugal’s two grid-capacity auctions, 750 MVA for standalone storage and 300 MVA for co-located, with a 50 MVA minimum bid and four hours at maximum injection power.
- Ireland: the CRU and EirGrid still have to build the framework behind the approved 500 MW long-duration procurement, which carries 10-year contracts, a revenue floor and 70:30 revenue sharing above it.
- Czechia: the ministry has proposed moving two supplementary capacity auctions open to storage from 2026 into 2027.
- The permitting directive: both institutions have to endorse the text before formal adoption, and member states then have a year and a half to transpose it.