Article · 11 November 2026
Sweden and Norway moved to end the Nordic reserve-market deal
Svenska kraftnät and Statnett gave notice on the agreement that underpins the joint Nordic aFRR and mFRR capacity markets and the mFRR energy market, with the dispute running on cost sharing. Litgrid opened a consultation on buying 800 MW of fast-start capacity on fifteen-year contracts, the Dutch cabinet set a 110 GWh storage benchmark and made flexible grid contracts the default for large batteries, and corporate buyers at RE-Source priced firmness while leaving the ancillary half of a battery alone.

Between 5 and 11 November, three transmission system operators and one government rewrote the terms on which flexible capacity gets bought. Svenska kraftnät and Statnett gave notice on the agreement behind the joint Nordic reserve markets, Litgrid opened a consultation on buying 800 MW of fast-start capacity under fifteen-year contracts, and the Dutch cabinet set a first national storage benchmark while making flexible grid contracts the default for large batteries. Underneath each of them sits the same argument about who carries the cost.
Two Nordic grid operators gave notice on the deal behind the joint reserve markets
Fingrid said on 6 November that Svenska kraftnät and Statnett have given notice to terminate the Nordic cooperation agreement on reserve markets, which ends in May 2027. That agreement is what enables the joint Nordic mFRR and aFRR capacity markets and the mFRR energy market, and Denmark's Energinet is a party to it alongside the other three. The four operators are preparing to begin negotiations on cost sharing for the services that keep those markets running.
Fingrid framed its own position carefully. It wants the cooperation to continue, wants broad and well-functioning reserve markets maintained, and wants a controlled transition to the European mFRR energy market in autumn 2027, in line with the original plan. It also said the possible termination is not expected to affect the adequacy of electricity supply in Finland or to have a significant impact on the operational security of the power system.
That autumn 2027 date is itself a revision. The Nordic Balancing Model programme said on 2 September that the Nordic change request to reduce the risk of undesired price spreads in MARI could not be reconciled with a first-quarter 2027 accession, and that September or October 2027 is now the most likely window. The same two capacity markets also change their bidding rules before any of this is settled: from 24 November the Indivisible Bids Allowed attribute disappears and Minimum Quantity becomes mandatory on every bid, so every bid counts as divisible unless its minimum is set equal to the offered quantity.
If you sell FCR, aFRR or mFRR capacity anywhere in the Nordics, your delivery obligations this winter are unchanged. What has changed is a planning assumption. A revenue model that treats one Nordic-wide auction as a fixed feature of 2027 now carries an open question, and it will be answered in a negotiation between four grid operators rather than by a market. Work out which of your revenue lines depend on cross-border clearing rather than on a national volume requirement, because those are the ones exposed if the shape of the joint markets changes. And test the 24 November bid change through every submission channel you use before it lands, since a missing minimum quantity stops a bid from the operational date of 25 November.
Fusebox aggregates distributed energy resources into portfolios that behave like one system, measurable and market-ready. The orchestration layer carries the groups, rules and participation logic across regions and TSOs, so which pool an asset bids into is a setting rather than a rebuild. When the arrangements behind one region's reserve markets are reopened, that layer is where the exposure gets managed.
Talk to Fusebox about your Nordic route to market →
Litgrid wants to buy 800 MW that can start inside half an hour
Lithuania's transmission system operator presented a concept for isolated-operation services on 10 November and opened a public consultation on it the same day. The design splits the country into seven energy islands covering Vilnius, Kaunas, Klaipėda-Mažeikiai, Panevėžys-Šiauliai, Alytus, Jurbarkas and Utena, each able to run on its own when the 330 kV transmission network is unavailable. Chief executive Andrius Šemeškevičius said the plan involves upgrading existing power plants, incorporating battery storage and installing new flexible generation where it is needed.
The procurement is the part that matters for anyone holding flexible capacity. Litgrid wants about ten new plants by 2033 with 800 MW between them, each between 50 MW and 100 MW, and each able to start operating within 30 minutes. Tenders will be technology-neutral and competitive, and winning bidders get five years to build and then provide the regional service for fifteen. The first auctions are expected in 2027 if the legislation and the regulatory changes pass, with private investors putting in around 880 million euros.
Litgrid will not run the plants. It buys an availability service from investors selected in commercial auctions on best price and recovers the cost from consumers through the transmission tariff, which it estimates will rise by 0.67 cent per kilowatt-hour after 2033. Outside an isolation event the plants sell their electricity on the market, provide balancing or produce heat, with no restriction imposed by the operator. Šemeškevičius expects gas to be the most popular bid for now, while hydrogen, biomethane and liquid fuels are all allowed. Litgrid's claim that the new capacity will also trim price peaks and average wholesale prices comes from the operator and has not been independently assessed.
For BESS owners and C&I operators in the Baltics, a second procured product is being written on top of the balancing stack while its terms are still open. Payment is for availability, and the asset keeps every other revenue line while it holds the obligation, which turns this into a compatibility question: can a 30-minute start and a long hold sit alongside the balancing capacity you already sell, without the two commitments landing on the same megawatts? That is the thing to settle before the consultation closes on 10 December, and the technical requirements are in the consultation for exactly that reason. If you want a first pass on how it would fit what your assets already do, Fusie can take the question.
Bring us your Baltic portfolio →
The Dutch cabinet set a storage benchmark and a default contract to go with it
Minister Stientje van Veldhoven and state secretary Jo-Annes de Bat sent the Beleidsagenda Energieopslag to the Dutch parliament on 9 November, setting a benchmark for new large batteries for the first time: 110 GWh of battery capacity in 2040, more than fifty times what stood at the end of 2025. The figure comes from the Nationaal Plan Energiesysteem, which pairs it with 28 GW of power, an average of four hours, and counts home batteries, standalone batteries, batteries co-located with renewable projects and vehicle-to-grid. Installed capacity at the end of 2025 was 2.1 GWh.
The agenda was drawn up with the grid operator association Netbeheer Nederland, the trade body Energy Storage NL, the regulator ACM and regional government, and it carries 25 actions. One of them changes how a project connects: grid operators will connect large batteries as standard on a capacity-steering contract or a redispatch contract, so that a battery is congestion-neutral at worst and congestion-relieving at best. ESS News reported the same intention as making flexible grid connection contracts the standard for large-scale batteries, alongside tariff and compensation structures that reward grid-conscious operation, without further specifics.
The money side is less settled. ACM is to examine whether extra discounts or exemptions on network tariffs for storage are justified, an exception that Germany and Belgium already grant. The ministry has reserved 35 million euros for 2027 to continue the Flex-e scheme and is exploring support for storage at solar parks through the SDE++. The agenda puts the prize at up to 4 billion euros of avoided network investment if storage is placed and operated with the grid in mind. RVO will track the 25 actions in an annual Monitor Energieopslag, and the letter to parliament says that if the roll-out structurally lags the benchmark, administrative and political choices follow.
If you are building or buying batteries in the Netherlands, read the default contract before you read the target. A capacity-steering or redispatch contract constrains when you can charge and discharge, and it is now the starting point for a new connection rather than a concession you negotiate your way into. The revenue question becomes how much value remains inside those windows, and the tariff question stays open until ACM reports. Price the two separately, and treat the 110 GWh headline as a statement of how much room the government intends to make rather than a forecast you can underwrite.
Let us look at dispatch under a flexible connection →
Corporate buyers moved to hybrids and left the ancillary half of a battery alone
Around 1,400 people spent 4 and 5 November at the Beurs van Berlage in Amsterdam for the tenth RE-Source, run by SolarPower Europe and WindEurope, with more than 350 corporate buyers in roughly 400 prescheduled meetings. The deal flow they came for is thinning: the RE-Source Platform said corporate power purchase agreements have secured 5.9 GW of renewable capacity in Europe so far in 2026, down 9.7% on the same period last year. ACER's Francesco Rossetto, presenting the agency's annual PPA assessment, described a market cooling down a little, with activity peaking in 2024 and the share of hours at very low power prices climbing from 1% to 2% in 2021 to around 10% now.
Solar is carrying most of that. LevelTen's Max Plumptre said capture rates in Spain and Germany have roughly halved since 2022. Pexapark put standalone solar PPA volumes down 43% this year and said almost a quarter of Spanish solar output has been generated during negative-price hours. Buyers responded by asking for more than one technology: nearly every request for proposals on LevelTen's platform this year included a hybrid product and about a quarter of its offers were hybrid, while Pexapark said multi-technology contracts have almost doubled.
Two sets of numbers from the floor say what firmness costs. Axpo's Domenico Franceschino gave indicative French tolling fees for seven to ten year contracts starting in 2029: about 80,000 euros per MW a year for a standalone battery, 65,000 for a co-located unit that can also charge from the grid, and 45,000 for one that charges only from on-site solar. He put cabling and grid fees in the standalone case at about 50,000 euros per MW a year against about 35,000 for the battery itself, which is to say the grid costs more than the hardware. Pexapark's Itamar Orlandi said the most valuable asset has become the grid connection point.
The limit on all of it is who trades what. Orlandi put half to two-thirds of a battery's value in ancillary services and said most corporates have neither the interest nor the capability to trade them. Statkraft's Silvia Escudero warned buyers that a battery's flexibility carries an opportunity cost, because grid services can be worth more than delivering power to a customer, and that a hybrid PPA is a good deal more complex than a solar PPA with a battery attached. One panellist noted that only one or two European countries issue guarantees of origin for stored electricity. For where the prices sit, LevelTen third-quarter data reported on 29 October put Spanish standalone solar PPAs at 30.93 euros per MWh against 48 euros for Spanish hybrids, with hybrid contracts recorded in nine European markets.
For PV and BESS owners selling into corporate contracts, the premium for a firmer shape is real and it stops well short of the full stack. A buyer will pay for delivery shaped the way their factory runs, and the same buyer will not take on the balancing products that carry most of what a battery earns. That makes the offtake conversation and the market-participation conversation two separate pieces of work, and bundling them into a single PPA tends to price the second one at zero. If you are structuring a hybrid now, size the ancillary layer on its own first, then decide how much of the asset the contract should cover.
Talk to us about the half a PPA will not buy →
What to watch
- 24 November: the Indivisible Bids Allowed attribute leaves the Nordic aFRR and mFRR capacity markets and Minimum Quantity becomes mandatory on every bid, applying from the operational date of 25 November (Nordic Balancing Model, 31 August).
- Autumn 2027: Nordic accession to MARI, with September or October the most likely window now that the first-quarter target has gone (Nordic Balancing Model, 2 September).
- 25 November and 10 December: Litgrid presents the isolated-operation concept to market participants, then closes the consultation, with an updated version expected in mid-January (LRT).
- Poland's regulator ran the 2026 auctions for new solar and onshore wind on 9 and 10 November, split between projects up to 1 MW and above, out of a programme worth about 24.9 billion zloty across more than 76 TWh. Results were not published at the time of writing (pv magazine).
- The ACM review of network-tariff discounts and exemptions for Dutch storage, and the annual Monitor Energieopslag that RVO is building with the grid operators and the sector (Solar & Storage Magazine, 9 November).
- End of 2028: the final revised GHG Protocol standard. Amazon Web Services told RE-Source that up to 35% of renewable energy contracts globally could be stranded unless the revisions protect deals already signed (ESS News).