Terna contracted 16 GWh of storage at 12% below its first auction
Terna awarded the full 16 GWh of Italy's second MACSE auction at 11,382 euros per MWh-year, below the lowest scenario published the day before, with the plants due in service in 2029. Poland capped how fast a battery may ramp into aFRR from 1 December, a German calculator put flexible connection agreements at up to 29% of a two-hour battery's revenue, NESO proposed buying response and reserve in twelve zones, and Spain approved its data-centre decree with hourly matching phased to 2032.

Terms moved in Italy, Poland, Germany, Britain and Spain in the seven days to 25 November 2026. Terna contracted another 16 GWh of Italian storage at a price below every scenario published before the auction, Poland and Germany tightened how fast a battery may ramp, Britain put locational procurement of response and reserve out to consultation, and Madrid approved the royal decree that conditions a large data centre's grid access on hourly renewable cover. Every one of those lands inside a business case somebody has already signed.
Italy's second storage auction cleared below every pre-auction scenario
Terna closed the second auction of MACSE, Italy's storage capacity procurement mechanism, on 24 November and awarded 16 GWh for delivery in 2029, the full volume it was looking for. The weighted average award price was 11,382 euros per MWh-year, against a reserve premium of 27,000 euros and 12% below the weighted average of the auction for the previous delivery year. About 67 GWh of new projects qualified and about 43 GWh was offered, so supply ran at close to three times the requirement. The awards went to lithium-ion batteries in four southern zones, with 9.6 GWh in the South and Calabria at 11,575 euros, 3 GWh in Sicily at 11,467 euros, 2.8 GWh in Centre South at 10,716 euros and about 0.5 GWh in Sardinia at 10,925 euros, and the contracted plants are expected in service in 2029 (ANSA).
The day before, Modo Energy market advisor Arthur Baltay had set out three scenarios for the same auction: about 24,000 euros per MWh-year with no existing capacity bidding and higher costs, about 21,000 euros with 8 GWh of existing capacity, and about 13,500 euros with 16 GWh of existing capacity and lower costs. He expected prices to come out higher than the first round rather than lower, and put the break-even for a brownfield project at around 13,900 euros against 27,000 euros for a greenfield plant relying on MACSE alone (ESS News). The clearing price landed under the lowest of the three scenarios. It arrived five days after Terna's first national flexibility assessment, which concluded that planned storage and renewable capacity can cover Italy's system needs through 2035, with 10.1 TWh of curtailment projected on the way (ESS News).
If you own or finance BESS in Italy, this auction has set the benchmark for what a 15-year Italian storage contract pays, and it is below what most models assumed. A project clearing at this level earns the rest of its return in day-ahead, intraday and ancillary markets around the contract, which makes the dispatch plan and the market access behind it the deciding factor in whether the premium is enough. If you are weighing the next round against staying merchant, price the stack first and the premium second, and check what the contracted asset can still trade while it is contracted.
Talk to Fusebox about revenue stacking around a capacity contract →
Poland and Germany put a speed limit on batteries
Poland's energy regulator URE approved a change to the transmission grid code of system operator PSE on 18 November, in force from 1 December. Providers of automatic frequency restoration reserve must still be fully activated within five minutes, but their ramp rate may not exceed their qualified control range divided by 2.5 minutes, so a battery can no longer reach full aFRR output faster than that. PSE says resources based on power electronics could otherwise activate in under a second and destabilise local networks, and that the cap is a domestic stability measure rather than a requirement of the European balancing platforms. The Polish Energy Storage Association asked for a system stability study, a periodic review of the limit, exemptions or an approach based on limiting overshoot, and PSE turned the request down. The same update splits manual frequency restoration reserve into a MARI-compatible standard product and a domestic non-standard one, and lets balancing service providers under 500 MW connect to PSE's load-frequency control through a remote node while streaming monitoring signals in real time, which the association welcomed as a lower barrier for smaller providers (ESS News).
In Germany the same limit arrives through the connection contract. Christian Schäfer of Regelleistung Online collected the flexible connection agreement terms published by eight network operators and built a calculator from them. It puts the revenue loss for a two-hour battery at 15% under N-Ergie's terms and 29% under Bayernwerk's, and at 11% to 20% for four-hour systems. Most of those agreements cap the gradient at the connection point at 6% of installed capacity per minute, which is close to 17 minutes from zero to full power. The gradient alone costs about 2.5% of wholesale revenue in the calculator, and it caps what a battery can prequalify for secondary control reserve at 30% of rated power, because the full contracted response has to arrive inside five minutes. Several operators also restrict discharge against a reference solar or wind output, and Bayernwerk starts restricting at 30% of that reference and stops discharge entirely at 60% (ESS News).
For BESS owners and for anyone aggregating C&I loads in either market, the number that decides your revenue is no longer the nameplate, it is what the grid code and the connection contract let you deliver inside five minutes. Prequalified volumes, bid sizes and the revenue model behind them all follow from that figure. Re-run prequalification against the new ramp arithmetic before the December delivery days, and look at whether the same assets earn more on a product with a slower response requirement. Our knowledge bot Fusie can walk through how a product's ramp rules translate into bid volumes if you want the detail before a call.
Ask Fusebox what your connection still lets you prequalify →
Britain moved on where a flexible asset registers and where it is paid
NESO launched its combined Reserve and Dynamic Response consultation on 20 November, open until 8 January 2027, with locational procurement as one of three sections alongside changes to the dynamic response tiered performance regime and housekeeping on reserve service terms (NESO). The proposal would add zones to the co-optimised day-ahead auction for response and reserve, twelve of them, three in Scotland and nine in England and Wales, drawn on transmission constraints, market liquidity and operational efficiency. Bids would be assessed against national and zonal requirements together, so the same service could clear at different prices in different zones while the network is constrained. New market participants would have to submit locational information, and individual and aggregated units would have to sit inside a single zone, although existing participants will not be put through onboarding again just to provide it (ESS News).
Registration itself is moving on a slower clock. Elexon, in its market facilitator role, has pushed the launch of flexibility market asset registration from September 2027 to spring 2028 after 21 of 27 consultation respondents said the sector was not ready for the earlier date. The service is meant to let an asset be registered once and used across markets, and NESO's data sharing infrastructure, the Demand Flexibility Service and DSO flexibility registration platforms all have to migrate onto it. Elexon has brought consistent asset allocation into the design and says it will give industry the detailed end-to-end plan by the end of January 2027 (Elexon).
If you aggregate small assets in Britain, two pieces of work are arriving together: proving where every unit sits on the network, and keeping its registration data consistent while the platforms underneath are rebuilt. A portfolio that straddles a zone boundary may have to be split before it can bid, and the asset data behind it has to survive a migration without anyone re-keying it.
Fusebox onboards assets into one standardised telemetry and command model, and makes that onboarding repeatable across fleets and third parties, so a new site or a new partner joins a portfolio the way the last one did. Controllers, forecasting tools and trading desks stay where they are and keep running as one flow. When a market changes what has to be declared about every unit, that is the layer where the change lands.
Bring Fusebox the asset data your markets are about to ask for →
Spain signed its data-centre decree and stretched the ramp to 2032
Spain's Council of Ministers approved the royal decree on energy, environmental, resilience and digital sovereignty requirements for data centres on 20 November, together with an updated transmission network development plan to 2030. Ecological transition minister Sara Aagesen said data centre projects already hold grid access for 15 GW, 6 GW on the transmission network and 9 GW on distribution, close to 40% of Spanish peak demand, with a further 20 GW waiting; the government's case is that unmanaged growth would add about 5 billion euros a year to system costs, 4 billion of it through wholesale prices and 1 billion through capacity mechanisms (pv magazine, Euronews). The network plan approved beside it carries 17.14 billion euros of investment and makes room for 47.4 GW of new demand, of which 9.3 GW is for data centres.
The approved text keeps the requirement and stretches the ramp. An optional transitional regime starts hourly correlation at 60%, raises it to 70% in 2029 and reaches 80% in 2032, and it is open to operators that accept being disconnected first when the system needs it. Failure to comply can bring financial consequences and, in some cases, suspension of access and connection rights for up to three years, while projects already being processed generally get six months to adapt. The decree takes effect when it appears in the official gazette (Data Center Dynamics).
If you run large loads in Spain, flexibility is now part of the price of a connection, and the softer compliance path is reserved for operators that agree to be curtailed first. That makes a site's ability to shed or shift load a negotiating position rather than an operational afterthought. If you own PV or storage, the additionality and hourly matching rules put a value on generation that can be matched to one consumer hour by hour, and on the storage that moves it into the hours the consumer actually uses.
Talk to Fusebox about matching a load to generation hour by hour →
Watch list
- 1 December, Poland. PSE's ramp cap and the split standard and domestic mFRR products start to apply, and the relaxed load-frequency control node rules open the market to smaller providers (ESS News).
- 8 January 2027, Great Britain. NESO's combined Reserve and Dynamic Response consultation closes, locational procurement included (NESO).
- End of January 2027, Great Britain. Elexon has promised the detailed end-to-end implementation plan for flexibility market asset registration (Elexon).
- Spain. Publication in the official gazette starts the clock, and projects already in process have six months to adapt (Euronews).
- 2029, Italy. The 16 GWh contracted this week is due in service, on a requirement approved by the environment ministry after an opinion from regulator ARERA (ANSA).
- EU flexibility needs assessments. A Compass Lexecon study for Eurelectric argues negative prices guide investment into storage and demand response only where support design and grid bottlenecks are not distorting them, as member states prepare their national flexibility needs assessments (pv magazine).